An Overview of Our Latest Rail Infrastructure Development Project

TGB’s Progress: Contracted for final construction documents for a Southeast Texas project

rail infrastructure development project

TGB Group specializes in rail infrastructure development projects.

TGB Group is proud to announce its latest milestone in collaboration with a valued customer in the Southeast Texas area. This partnership showcases TGB’s commitment to delivering exceptional results in the realm of rail infrastructure development.

Originally entrusted with the task of producing 30% design documents and a preliminary budget estimate in November 2022, TGB’s expertise in design and planning came to the forefront. These documents, along with the budget estimate, were meticulously crafted to align with the customer’s vision, requirements and project goals for rail infrastructure development.

In March 2023, TGB delivered these documents, marking a crucial step in the project’s journey.

In a clear demonstration of our team’s commitment and skill, the customer reaffirmed their trust in May 2023 by granting the Notice to Proceed (NTP) for the creation of final construction documents. This significant step not only solidified the partnership but also showcased the unwavering confidence in TGB’s capability to transform ideas into concrete outcomes.

Rail infrastructure development scope

The scope of this ambitious design project includes:

  • 28,900 track feet of rail to secure connectivity and efficient transportation
  • 23 turnouts to help smooth transitions and maneuverability
  • 15,000 steel ties, components that are required for structural integrity
  • 21,500 tons of ballast to contribute to stability and longevity
  • 29,000 tons of sub ballast, a foundation for the project’s durability
  • A significant number of culverts, thoughtfully sized for effective drainage solutions

Anticipation grows as the project prepares for its next phases. With plans to initiate the bidding process in January 2024, the construction stage will launch in March 2024 and should run for nine months.

TGB’s attention to detail, adherence to deadlines and commitment to quality in this project set the stage for a successful and transformative endeavor.

For additional information about this rail infrastructure development project or other TGB Group projects, contact Steven Surratt, Business Development, at (817) 487-0193.