Survey and Design Project for Chemical Company
Completion of the project expected in late 2021

- Demolition
- Site civil
- Rail construction
Survey and design project specs
The demolition portion of the project began with a pre-construction meeting between TGB Group and the selected contractor on August 3, 2021. Demolition began on August 7.
Now that the demolition phase is complete, the contractor is working on the site/civil and rail portion of the project, which is expected to be completed in late November or early December 2021.
The rail portion of this survey and design project consists of rehabilitating the existing turnout and the existing 1,100 feet of lead track as well as adding more than 1,700 feet of new track and a single new turnout.
There will be a storage track for cars to be spotted on as well as an unloading track for the chemicals to be unloaded from the rail cars for the facility to use.